Item Coversheet
 ITEM: 4.K.
COUNCIL MEETING DATE:
October 8, 2015
SECTION:Consent Agenda
Description:
Approve Change Order No. 1 to Agreement with Geislinger and Sons, Inc., for Project 2014-129, Sanitary Lift Station 3 Replacement
Staff Contact:
Carol Blommel Johnson, Public Works Superintendent - Utilities
Department / Division:
Utilities Division

ACTION REQUESTED:

Motion to approve Change Order No. 1 to the agreement with Geislinger and Sons, Inc., for Project 2014-129, Sanitary Lift Station 3 Replacement by adding the amount of $5,645.00. 

  

SUMMARY:

The 18" storm sewer line from Chaparral Drive to Pond BD-P140 needs to be extended to the pond. The existing piping and flared end no longer provide proper drainage due to low elevation and sediment. The additional work included in this change order will bring the storm sewer piping to the edge of the pond resolving drainage issues.  This work is being proposed now while the site is under construction for the lift station project.  The work could be included in a future street project but would require disrupting the same area that is currently under construction.

 

BACKGROUND:

On April 9, 2015, the City Council approved an agreement with Geislinger and Sons, Inc. to replace the aging lift station. 


BUDGET IMPACT:

Funding for the extension of the storm sewer line will be from the Storm Water Utility budget, 5505-6269D.
 
ATTACHMENTS:
Type
Change Order Document(s)