Item Coversheet
 ITEM: 4.J.
COUNCIL MEETING DATE:
October 8, 2015
SECTION:Consent Agenda
Description:
Adopt Resolution Authorizing Preparation of Plans and Specifications for Project 2016-106, 2016 Micro Surfacing
Staff Contact:
Brandon Anderson, Acting City Engineer
Department / Division:
Engineering Division

ACTION REQUESTED:

Adopt resolution authorizing preparation of plans and specifications for Project 2016-106, 2016 Micro Surfacing. 

  

SUMMARY:

The City of Apple Valley 2016 Capital Improvement Program identifies $995,000 for street preservation in the form of micro surfacing.  Attached for consideration is a resolution ordering plans and specifications for Project 2016-106, 2016 Micro Surfacing.  It is anticipated that approximately 246,000 square yards of street will be micro surfaced including portions of the following neighborhoods and streets:

 

  • Briar Oaks 1st and 2nd
  • Oaks of Apple Valley III
  • Diamond Valley Estates
  • Eagle Ridge Estates
  • Greenleaf Park Estates
  • Scottsbriar 1st and 2nd
  • Summerfield 1st, 2nd, and 3rd
  • 140th Street W

 

The locations of the proposed improvements are identified on the attached map (Figure: 1).

 

BACKGROUND:

The work consists of applying a thin wear-resistant layer of oil and rock mixture that helps prevent pavement oxidation and seepage of moisture into the pavement surface.

 

Following is a summary of anticipated project costs and funding sources:


BUDGET IMPACT:

Estimated Project Costs:

 

 

 

Construction Cost

$935,000

 

Construction Contingency

$20,000

 

Engineering Design

$25,000

 

Inspection

$15,000

 

Total Estimated Cost

$995,000

 

 

 

Estimated Project Funding:

 

 

 

Municipal State Aid

$535,000

 

Road Improvement Fund

$460,000

 

Total Estimated Funding

$995,000


 
ATTACHMENTS:
Type
Map
Resolution