Description: Adopt Resolution Authorizing Preparation of Plans and Specifications for Project 2016-106, 2016 Micro Surfacing | Staff Contact: Brandon Anderson, Acting City Engineer | Department / Division: Engineering Division |
|
| | | | | | | | ACTION REQUESTED:
Adopt resolution authorizing preparation of plans and specifications for Project 2016-106, 2016 Micro Surfacing.
SUMMARY:
The City of Apple Valley 2016 Capital Improvement Program identifies $995,000 for street preservation in the form of micro surfacing. Attached for consideration is a resolution ordering plans and specifications for Project 2016-106, 2016 Micro Surfacing. It is anticipated that approximately 246,000 square yards of street will be micro surfaced including portions of the following neighborhoods and streets:
- Briar Oaks 1st and 2nd
- Oaks of Apple Valley III
- Diamond Valley Estates
- Eagle Ridge Estates
- Greenleaf Park Estates
- Scottsbriar 1st and 2nd
- Summerfield 1st, 2nd, and 3rd
- 140th Street W
The locations of the proposed improvements are identified on the attached map (Figure: 1).
BACKGROUND:
The work consists of applying a thin wear-resistant layer of oil and rock mixture that helps prevent pavement oxidation and seepage of moisture into the pavement surface.
Following is a summary of anticipated project costs and funding sources: BUDGET IMPACT:
Estimated Project Costs:
|
|
|
|
Construction Cost
|
$935,000
|
|
Construction Contingency
|
$20,000
|
|
Engineering Design
|
$25,000
|
|
Inspection
|
$15,000
|
|
Total Estimated Cost
|
$995,000
|
|
|
|
Estimated Project Funding:
|
|
|
|
Municipal State Aid
|
$535,000
|
|
Road Improvement Fund
|
$460,000
|
|
Total Estimated Funding
|
$995,000
|
|
|
|